148 Old Street
Client: Great Portland Estates | Duration: 47 Weeks | Value: £4,700,000

Cantillon have been appointed by Great Portland Estates to undertake partial demolition, structural alterations and enabling works package for 148 Old Street. Previously the location of the Old Street Royal Mail Sorting Office, after refurbishment the building will deliver 151,000 sq. ft. of high quality office space.

READ MORE DOWNLOAD CASE STUDY

100 City Road – White Collar Factory
Client: Derwent | Duration: 32 Weeks | Value: £3,000,000

As the only contractor to identify problematic issues at tender stage and offer a well executed programme, Cantillon were awarded the 100 City Road project from Derwent. The site was located between City Road and Old Street roundabout junction and consisting of five buildings, each of varying size and construction. The largest building, 9-storey Transworld […]

READ MORE DOWNLOAD CASE STUDY

Stonebridge Estate
Client: Hillside Housing | Duration: Phased Works | Value: £20,000,000

For over eight years, Cantillon Ltd worked in a framework partnership with the Stonebridge Housing Action Trust and Hillside Housing throughout their regeneration of the Stonebridge Estate in North West London. The development of new dwellings for all residents and a variety of community facilities required a huge programme of phased demolition and construction works.

READ MORE DOWNLOAD CASE STUDY

New Fetter Lane
Client: GPE | Duration: 44 Weeks | Value: £5,100,000

Cantillon were appointed as Principal Contractor by GPE to deliver the demolition and enabling works package for the development of 12-14 New Fetter Lane.

READ MORE DOWNLOAD CASE STUDY

Davies Street
Client: GrosvenorStow | Duration: 32 Weeks | Value: £1,500,000

Cantillon completed the soft strip, asbestos removal and demolition of the seven storey commercial space located over a single-story retail block with approximately GEA 103,500 SqFt.

READ MORE DOWNLOAD CASE STUDY

Chiltern Street
Client: Ronson Capital Partners | Duration: 42 Weeks | Value: £4,070,000

In the heart of Marylebone, London, the 12 story International House building was demolished to make way for RCP’s Chiltern Street residential scheme. The project consisted of asbestos removal, soft strip works and floor by floor demolition. Permanent sheet piles were placed and capped in advance of a large bulk excavation package excavation.

READ MORE DOWNLOAD CASE STUDY

Gypsy Corner
Client: Frogmore Developments | Duration: 32 Weeks | Value: £2,000,000

Cantillon were appointed by Frogmore Developments as Principal Contractor to carry out the demolition and decontamination of the brownfield site at Gypsy Corner, Acton, London W3.

READ MORE DOWNLOAD CASE STUDY

Foreign & Commonwealth
Client: MACE | Duration: On-Going | Value: £372,500

The Cantillon Asbestos Division undertook the challenging Foreign & Commonwealth project within a part live building, where background checks had to be made in advance and daily security inspections undertaken. This work is made up of a series of sequential visits, returning when each relevant work space has been vacated.

READ MORE DOWNLOAD CASE STUDY

Oxford Street, London

A facade retention and jacking scheme, delivered on behalf of GPE and Multiplex. Cantillon’s engineering team designed and managed the jacking scheme which involved raising a 200 tonne terracotta façade by c.900mm.

DOWNLOAD CASE STUDY

Tate Modern, Southwark
Client: Mace | Duration: 35 Months (Phased) | Value: £12,200,000.

Cantillon delivered the demolition and piling package to the Existing Bankside substation in 2010. This paved the way for the 1st Phase of the Transforming Tate Modern project and the creation of the ‘Oil Tanks’ Space.

DOWNLOAD CASE STUDY