On Site @ Thames Tideway Tunnel

July 16, 2020

The Kirtling Street building has been fully demolished, commencing Monday the Asbestos Division have 2-3 days notifiable asbestos removal. Following this a snagging will be carried out and completion on that part of site will be mid-April.

On the 2a Battersea Park Road site, the welfare remains and the building is fully demolished, this area is being used for processing the materials and clearing the hard core to be recycled and removed from site.

The project is due to be completed in May.