On Site @ Seymour Street

July 16, 2020

Having commenced in March, Seymour Street is now undergoing the soft strip prior to demolition. The asbestos removal is happening in conjunction with the soft strip. All asbestos is non-notifiable.

Scaffold erection is currently underway to the internal courtyard and Bryanston Street gantry. The hoarding has been completed around the site perimeter of Bryanston Street and Seymour Street although lighting is being completed next.

Meanwhile structural investigations are being carried out for further understanding the party wall conditions.