On Site @ Chiltern Street

July 16, 2020

The demolition is now completed and the 2 storey basement has now been fully excavated, whilst basement level 2 was passed over on 7th April for the Ground Source Heat Pump piling to start.

Following the first stage of piling we will go back into the basement to form the trenches for the heating pipes to the main manifold and concrete them in.

At the Basement Level 1, Cantillon have been completing the ground bearing slab removal for the new townhouse in the SW corner and cutting down the top of the retaining wall for new slab construction to the north elevation following demolition of our former loading bay slab.