Cantillon started on site on 6th January 2014. The enabling works are now fully underway within the large project consisting of five buildings. The hoarding is currently being erected around the perimeter of the whole site on kentledge concrete blocks.

The scaffolding is also being erected around the largest building, Transworld House, along the City Road elevation.
Inside the buildings all the A/C Units have been de-gassed which took place at the same time as the soft strip commenced and continues throughout all buildings except for Featherstone House, which will remain standing until it’s refurbished separately at the end of the project.
Demolition has commenced on the entrance to the dis-used car park off Mallow Street for improved access to Transworld House.
Updates will follow throughout the project.